How to Manage Authority Design Submissions

An authority rejection rarely starts with one missing note on a drawing. More often, it begins when the structural assumptions, MEP loads, fire strategy, utility constraints and drawing revisions stop telling the same story. To manage authority design submissions well, a project team needs a controlled technical process. That process makes compliance visible, coordinates every discipline and keeps a defensible record of decisions.
For developers, contractors and asset owners, this is not paperwork. Authority approval drives procurement, site mobilisation, utility connections, construction sequencing and final occupancy. A package that is technically sound but poorly coordinated can still lose weeks in review cycles. The goal is not simply to submit documents. Instead, it is to submit evidence that an approving engineer can review, verify and accept without rebuilding the design intent.
Plan Authority Design Submissions Around the Approval Pathway
Set the submission programme during design planning, before detailed production starts. Each authority has its own stages, forms, discipline interfaces, review periods and resubmission rules. In the UAE, for example, the municipality, the roads authority, Civil Defence and the utility providers may each need a different approval sequence. Permitting agencies in Kuwait, Saudi Arabia and other markets work the same way.
Next, create a submission register. For each package, it should record the approving body, the package title and the project stage. It should also list the required deliverables, the responsible discipline, the planned issue date, the review status and the closeout owner.
In addition, the register should show dependencies. A drainage layout may depend on approved road levels. A fire pump room may depend on confirmed electrical loads and Civil Defence criteria. Likewise, a bridge substructure package may depend on geotechnical parameters, hydraulic clearance and highway design criteria.
The register works best as a live engineering control, not as a project management tracker. Tie every date to a technical readiness condition. A package with open load paths, missing utility data or an unapproved design basis is not ready, even if the drawing set looks complete.
Define a Code and Design Basis Reviewers Can Check
Approving engineers need to see which rules govern the design and how the team applied them. A clear design basis report states the location, design life, occupancy or asset class and environmental exposure. It also sets out the loading criteria, material specifications, analysis method and governing codes.
For structural packages, the basis may cite ACI 318 or Eurocode 2 for concrete and AISC 360 or Eurocode 3 for steel. Bridges add the AASHTO LRFD specifications [1]. It should also give wind and seismic parameters, geotechnical design values, durability provisions and fire resistance criteria. For MEP packages, it should define electrical demand, short-circuit levels, HVAC design conditions, ventilation rates and plumbing demand. Drainage criteria, fire water storage, pump duties and life safety interfaces complete the list.
Show the Code Applied, Not Just Named
A code reference in the general notes is not enough. The submission should show how the team applied it. For a retaining wall with a surcharge, state the adopted value and its source. If moment, shear, axial force and buildability govern a steel connection, show the design actions and the connection checks. If a smoke control strategy relies on pressure differences or extract rates, name the design scenario and the acceptance criteria, for example under NFPA 92 [2].
A reviewer should be able to trace a critical result from the authority requirement, through the design assumption, to the calculation and the drawing detail. That traceability makes a decision defensible to any authority. In UAE projects, the fire and life safety elements must also trace back to the UAE Fire and Life Safety Code of Practice [3].
How to Manage Authority Design Submissions Across Disciplines
Many submissions fail at the discipline interfaces. Structural, architectural, civil, electrical, mechanical, plumbing, fire protection and specialist systems may each be correct alone. Yet the combined package can still be unbuildable or noncompliant.
So start coordination from controlled base information. Fix the approved grid, levels, site benchmark, plot boundary, road alignment, utility corridors, architectural model version and model coordinates. A small level discrepancy becomes a major issue where road drainage, basement ramps, external works and building thresholds meet.
Then review the interfaces that carry approval risk. Typical examples include slab openings, MEP penetrations, fire-rated shafts and equipment maintenance clearances. Others are transformer and generator ventilation, fire truck access and pump room drainage. On infrastructure, look at bridge utility crossings, gantry foundations and utility conflicts with culverts or retaining walls. Our articles on MEP drawing coordination and MEP riser coordination cover two of these interfaces in depth.
A federated BIM model makes these risks visible, but clash detection alone is not enough. Not every clash matters, and not every authority issue appears as a clash. The review must therefore test compliance intent. Does the fire access route still work after final landscaping? Does the electrical room keep its clearance after the structure thickens? Can the drainage route reach its invert level without hitting the foundations?
Model Exchange for Remote BIM Teams
For remote BIM delivery, define the model exchange protocol at the outset. It should fix the model origin, file naming, revision status, level of development and any IFC exchange needs. It should also name who closes each coordination comment. ISO 19650-2 sets out this delivery process. In it, the lead appointed party reviews and authorises the model before the client accepts it [4]. A model with unclear authorship or uncontrolled revisions creates approval risk, even when the geometry is right. Our IFC interoperability article covers the exchange rules.
Issue One Coordinated Package
An authority submission should read as one package, not as a set of discipline outputs. The cover letter, document index, drawing register, reports, calculations, models, specifications and forms must share the same project data and revision references.
Set a document hierarchy before issue. The approved design basis and the authority conditions govern the calculations. Next, the calculations govern drawing dimensions and the reinforcement or equipment schedules. The drawings, in turn, govern construction intent. Resolve every discrepancy before submission. Do not leave it for the reviewer to find.
The same control applies to contractor shop drawing submissions. A reinforcement drawing must match the latest structural drawings, architectural openings, embedded items, bar marks, construction joints and bar bending schedule. Similarly, a steel fabrication package must match member releases, connection forces, bolt grades, weld requirements, erection assumptions and interface tolerances. Drawing on the client’s title block is easy. Keeping revision integrity across the whole package is the real technical duty, whether the work sits in-house or with an external drawing office.
Check Design and Documents Separately
Run an internal pre-submission check with two separate parts. Design verification confirms that the calculations, load cases, analysis model and detailing assumptions are correct. Document verification confirms signatures, current references, mandatory forms, and revision clouds that follow the authority procedure. ISO 9001’s design and development controls ask for the same split between reviews, verification and validation [5].
Treat Review Comments as Engineering Actions
Do not circulate authority comments as an unstructured email chain. Instead, log each comment with its source, discipline, technical issue, required action, response owner, target date and closure evidence. Above all, keep each response short but specific.
A weak response says, “Noted and revised.” A controlled response names the change. For example: “Foundation schedule revised to the geotechnical allowable bearing pressure of 250 kPa. Footing sizes and punching shear checks updated in calculation package revision C, sheets S-421 to S-426.” The reviewer can then confirm closure quickly, and repeat comments fall.
Some comments force a design change that reaches beyond the marked drawing. A larger water tank, for instance, changes dead load, support reactions, electrical demand, pump duty and perhaps room size. Moving a utility corridor may change the pavement build-up, drainage crossings and chamber positions. For this reason, the comment log should trigger an impact check whenever a change crosses discipline lines.
When a comment is ambiguous or seems to conflict with the stated code, ask for clarification early. Do not build a large resubmission on an assumed reading. A short technical meeting with marked-up drawings and a focused code reference can save weeks of redesign.
Protect Authority Design Submissions After Approval
However, approval does not freeze every design decision. Value engineering, site conditions, material substitutions, utility revisions and construction sequencing often bring changes later. The risk is that the site builds from a revision that no longer matches the approved package.
Keep an approval matrix that separates permit documents, construction issue documents, shop drawings, temporary works and field change notices. Assess any change that affects code compliance, structural capacity, egress, fire protection, utility connections or public safety for resubmission before it reaches site. ISO 9001 treats this as design change control, with a record of each review [5].
This matters most on existing assets. Strengthening works, load rating decisions and rehabilitation details often rely on inspection findings, material tests, reinforcement scans, monitoring data or assumptions about hidden conditions. If site evidence changes the engineering basis, the authority record may need to change with it.
At Engineering Support Group (ESG), we prepare design and shop drawing packages to this standard for contractors and asset owners in the UAE, Kuwait and Saudi Arabia. Each package carries its design basis, calculation references and comment log together.
Authority Design Submissions Checklist
- Submission register with approving body, deliverables, owner, dependencies and readiness condition for each package.
- Design basis report naming the governing codes and the adopted values.
- Critical results traceable from requirement to assumption, calculation and drawing.
- Controlled base information: grid, levels, benchmark, coordinates and model versions.
- Document hierarchy agreed, and every discrepancy closed before issue.
- Separate design verification and document verification records.
- Comment log with owners, dates, closure evidence and impact checks.
- Approval matrix that screens every later change for resubmission.
The most reliable submission process leaves reviewers less to infer and project teams less to recover later. Build the evidence trail early, control every interface and answer each comment with proof. Approval then becomes a managed engineering outcome, not a late-stage gamble.
References
- ACI CODE-318-19, Building Code Requirements for Structural Concrete; ANSI/AISC 360-22, Specification for Structural Steel Buildings; AASHTO LRFD Bridge Design Specifications, 10th edition (2024). concrete.org AASHTO Journal
- NFPA 92, Standard for Smoke Control Systems, 2024 edition, National Fire Protection Association. NFPA
- UAE Fire and Life Safety Code of Practice, 2018 edition, Ministry of Interior, General Command of Civil Defence.
- ISO 19650-2:2018, Organization and digitization of information about buildings and civil engineering works, including BIM, Part 2: Delivery phase of the assets, clause 5.7. iso.org
- ISO 9001:2026, Quality management systems: Requirements, design and development requirements. Replaces ISO 9001:2015. iso.org